Stickle Ghyll, Langdale
100kW, Langdale, Cumbria
A 100kW project in Langdale, Lake District, working closely with the National Trust.
Site: | Stickle Ghyll, Langdale |
---|---|
Consenting timeline: | Nov 2012 – Dec 2013 |
Construction timeline: | 2014-2015 |
Location: | Lake District |
Turbine: | Gilkes Turgo 13.5″ |
Generator: | 122kVA Induction |
Grid: | 200kVA transformer |
Intake type: | Half height Coanda screen |
Gross head: | 77 metres |
Catchment area: | 2.4 km2 |
Max turbine flow: | 0.184m3/s |
Max output: | 100 kW |
Pipeline length: | 160 metres |