Rydal Beck
500kW, Cumbria
A 500kW high head project on Rydal Beck near Ambleside and Windermere, the tourism hub of the Lake District.
Site: | Rydal Beck |
---|---|
Consenting timeline: | June 2012– Dec 2013 |
Construction timeline: | 2014-2015 |
Commissioning date: | August 2015 |
Location: | Lake District |
Turbine: | Gilkes Turgo |
Generator: | Synchronous |
Intake type: | Coanda screen |
Gross head: | 99m |
Catchment area: | About 6.6km2 |
Max turbine flow: | 690lps |
Max output: | 500kW |
Penstock length: | ~710m |