Mill Beck Old Hutton
60kW, Cumbria
A 60kW low/med head project to provide a dependable income stream on a farm
Site: | Mill Beck Old Hutton |
---|---|
Consenting timeline: | Sept 2011 – December 2013 |
Construction timeline: | 2013-2015 |
Commissioning date: | June 2015 |
Location: | Lake District |
Turbine: | Ecowave Crossflow |
Generator: | 3 phase asynchronous generator |
Grid: | 3 Phase, 80kVA PMT |
Intake type: | Coanda Screen |
Gross head: | 15m |
Catchment area: | 16.8km2 |
Max turbine flow: | 750lps |
Max output: | 60kW |
Pipeline length: | 290m |