Halton Gill
44kW, Yorkshire
A 40kW project in the Yorkshire Dales National Park
Site: | Halton Gill |
---|---|
Consenting timeline: | March 2009 – July 2010 |
Construction timeline: | September 2010 –March 2011 |
Commissioning date: | May 2011 |
Location: | Yorkshire Dales |
Turbine: | Gilkes Compact Turgo Impulse |
Generator: | 1500 rpm Induction Generator |
Grid: | Single phase, 50 kVA PMT |
Intake type: | Coanda D-1200 |
Gross head: | 79m |
Catchment area: | 0.92km2 |
Max turbine flow: | 80lps |
Max output: | 44kW |
Pipeline length: | 500m |