100kW, Cumbria
A 100kW high head project on Greenburn, Little Langdale, Cumbria. This scheme is being developed by the National Trust, with Ellergreen providing the consenting works.
Site: |
Greenburn Beck |
Consenting timeline: |
Aug 2015– March 2016 |
Construction timeline: |
2016 – 2018 |
Commissioning date: |
September 2018 |
Location: |
Lake District |
Turbine: |
Turgo |
Generator: |
Synchronous |
Intake type: |
Coanda screen |
Gross head: |
144.5m |
Catchment area: |
About 2.6km2 |
Max turbine flow: |
94lps |
Max output: |
100kW |
Penstock length: |
1.1km |