Fisherplace Gill
395kW, Cumbria
A 395kW project on the east side of Thirlmere, our highest head scheme to date.
Site: | Fisherplace Gill |
---|---|
Consenting timeline: | August 2013– Summer 2015 |
Construction timeline: | 2015-2016 |
Commissioning date: | September 2016 |
Location: | Lake District |
Turbine: | Pelton |
Generator: | 439kVA Synchronous |
Intake type: | Full height Coanda screen |
Gross head: | 221.97 |
Catchment area: | 2km2 |
Max turbine flow: | 205lps |
Max output: | 395kW |
Penstock length: | ~810m |