Yew Beck
5kW, Cumbria
A domestic scale 5kW scheme near Rusland, Cumbria. This scheme is being aided by Ellergreen through the design & consenting phase.
Site: | Yew Beck |
---|---|
Consenting timeline: | May 2012– Dec 2013 |
Construction timeline: | 2014-2015 |
Commissioning date: | October 2015 |
Location: | Rusland, Cumbria |
Turbine: | Turgo |
Generator: | tbc |
Intake type: | Coanda screen |
Gross head: | 11.24m |
Catchment area: | About 1.14km2 |
Max turbine flow: | 62lps |
Max output: | 5kW |
Penstock length: | 71m |