Kentmere Hall
60kW, Cumbria
A 60kW high head scheme on historic hill farm
Site: | Kentmere Hall |
---|---|
Consenting timeline: | Feb 2011– July 2011 |
Construction timeline: | August 2011 to December 2011 |
Commissioning date: | 21/02/2012 |
Location: | Lake District |
Turbine: | Gilkes Pelton |
Generator: | 3 phase asynchronous generator |
Grid: | 3 Phase, 80KVA Pad mounted transformer |
Intake type: | Coanda Screen |
Gross head: | 128m |
Catchment area: | 4.7km2 |
Max turbine flow: | 60lps |
Max output: | 60kW |
Pipeline length: | 650m |