30kW, Cumbria
A 30kW project in Longsleddale, Cumbria. The second scheme Ellergreen installed in the Longsleddale valley.
Site: |
Kilnstones, Longsleddale |
Consenting timeline: |
Jan 2010 – Feb 2010 |
Construction timeline: |
Feb 2010 – July 2011 |
Commissioning date: |
August 2011 |
Location: |
Longsleddale, Lake District |
Turbine: |
Gilkes Pelton |
Generator: |
1000 rpm Induction |
Grid: |
Single Phase, 50 kVA PMT |
Intake type: |
Coanda Type E – 1000 |
Gross head: |
111m |
Catchment area: |
0.76km2 |
Max turbine flow: |
35lps |
Max output: |
30kW |
Pipeline length: |
350m |