100kW, Snowdonia
A 100kW high head scheme in the Snowdonia National Park in North Wales. This scheme is being developed for the National Trust.
Site: | Afon Berthen |
---|---|
Consenting timeline: | Nov 2012 – Feb 2014 |
Construction timeline: | 2015 – 2016 |
Commissioning date: | Autumn 2016 |
Location: | Bethesda, North Wales |
Turbine: | Hydrolite Turgo |
Generator: | Induction |
Intake type: | Coanda screen |
Gross head: | 174m |
Catchment area: | 1.56km2 |
Max turbine flow: | 84lps |
Max output: | 100kW |
Penstock length: | 650m |